Spent on Infrastructure

Engineering

  2015 2016 2017 2018
Progress 6,699,043 4,184,697 3,556,356 6,549,236
Goal 6,170,000 4,050,000 4,050,000 7,776,341
 

What are we tracking?

1. 26th Street Watermain Replacement & Road Reconstruction, 2. Street Resurfacing (various locations), 3. 16th Street North, 17th Street North and 18th Street North Watermain Replacements, 4. Elmdale Boulevard & Spruce Drive Watermain Replacements 5. Richmond Avenue & 22nd Street Watermain Replacements and Land Drainage Improvements.

 

 

How are we measuring this?

Measurements are made at the end of each month for progress payments, the value of work completed compared to the total budget gives an indication of percentage of work complete.

What progress are we making?

Most recent progress as of September 30, 2018 indicate all projects are either completed or on track to be completed by the end of the year.
 